Repair of the automatic level crossing
As some visitors may have noticed, on the way to the "Nonnewisen" station there is a level crossing with 2 control lamps for the driver. However, this system has not worked for several years. The first problem that had to be fixed was the power line. For this purpose, a 230V line was laid from the Nonneweisen switch tower to the crossing.
Now came the real challenge. The crossing is operated automatically: the rails between 2 separate places work like a large switch. To do this, however, the rails must be connected to one another. So connections had to be welded on again. About 60 pieces were installed.
Now everything works as it should again. Fully automatic: